Crestview Road rehabilitation
Virtual Open House
Background
Crestview Road will be rehabilitated starting at the intersection of North Frontage Road and Crestview Road continuing north approximately 2.50 miles to .35 miles past the railroad tracks.
The existing roadway is 24 feet wide. The rehabilitation project will have 24-foot wide pavement with 1 foot gravel shoulder on both sides of the road.
During construction Crestview Road will be reduced to one lane and construction will last approximately 8-10 weeks.
timeline
preliminary
design
Design
Complete
summer 2021
Construction
2026/2027
Fall 2020
PLease note: dates are tentative and subject to change

Conceptual
typical
sections
North Frontage Rd. to 750 South
The existing roadway will remain 24 feet wide. White edge lines will be installed and 1 foot gravel shoulders.